- In order to meet environmental flows and levels, every regional council:
- must identify take limits for each FMU; and
- must include the take limits as rules in its regional plan(s); and
- must state in its regional plan(s) whether (and if so, when and which) existing water permits will be reviewed to comply with environmental flows and levels; and
- may impose conditions on resource consents.
- Take limits must be expressed as a total volume, a total rate, or both a total volume and a total rate, at which water may be:
- taken or diverted from an FMU or part of an FMU; or
- dammed in an FMU or part of an FMU.
- Where a regional plan or any resource consent allows the taking, damming, diversion or discharge of water, the plan or resource consent must identify the flows and levels at which:
- the allowed taking, damming, or diversion will be restricted or no longer allowed; or
- a discharge will be required.
- Take limits must be identified that:
- provide for flow or level variability that meets the needs of the relevant water body and connected water bodies, and their associated ecosystems; and
- safeguard ecosystem health from the effects of the take limit on the frequency and duration of lowered flows or levels; and
- provide for the life cycle needs of aquatic life; and
- take into account the environmental outcomes applying to relevant water bodies and any connected water bodies (such as aquifers and downstream surface water bodies), whether in the same or another region.
[…]
take limit means the limit on the volume, rate, or both volume and rate, of water that can be taken or diverted from, or dammed in, an FMU or part of an FMU, as set under clause 3.17.
Meeting the environmental flows and levels requires councils to restrict the taking, damming, diverting and discharging of water through ‘take limits’.
Take limits must:
- be expressed as a rule in the regional plan, and be set for every FMU
- achieve the flows and levels for an FMU. They should not allow flows or levels of water to fall below these
- be expressed as a volume or rate of take, or both. For example: ‘No more than xx m³/s can be taken from this river from 1 November to 31 March’. Groundwater may be expressed as maximum annual volume taken.
Where a regional plan or water permit allows the taking, damming, diversion or discharge of water, it must identify the flows and levels at which these activities will be restricted, no longer allowed, or in the case of discharges, required (clause 3.17(3)).
Take limits must also:
- provide for flow or level variability that meets the needs of the water body from which the water is taken or diverted, or in which it is damned, and the needs of connected water bodies, and their associated ecosystems (eg, a groundwater take limit would not cause a permanent lowering of the groundwater levels, or reduce connected river flows below their environmental flow)
- safeguard ecosystem health from effects on the frequency and duration of lowered flows and levels (eg, a river system may have two or more take limits, so that restrictions can be applied in stages according to the flows and levels)
- provide for the life cycle of aquatic life (eg, a river system may have multiple take limits and restrictions applied to each limit, according to seasons or flows or both)
- take into account environmental outcomes for relevant and connected water bodies (eg, a groundwater take limit may be set so that water levels in a connected wetland maintain the conditions necessary for the wetland flora or fauna)
- be able to quantify for freshwater accounting purposes (clause 3.29) and know total takes for every FMU.
These provisions work closely with Policy 11: Freshwater is allocated and used efficiently, all existing over-allocation is phased out, and future over-allocation is avoided. This has been retained from previous versions of the NPS-FM. The provisions also link to the requirements in clause 3.28 to provide for the transfer of water takes and how to improve efficiency of water use.
Over-allocation
An important part of the definition of ‘over-allocation ’ or ‘over-allocated’ is where resource use exceeds a limit and where an FMU or part of an FMU is not achieving an environmental flow or level set for it under clause 3.16. ‘Limit’ includes a ‘take limit’. Take limits act in tandem with other restrictions such as cease-to-take flows. For example, it may be environmentally conservative to allow a large rate of take for filling a storage pond during higher flows, in order to limit water abstraction at lower flows. However, this would require applying a cease-to-take flow to stop filling of the storage outside relatively high flows. In this situation, two cease-to-take limits would be applied: one to limit water abstraction at lower flows and the other to high-flow harvesting.
In combination, these definitions mean that councils cannot make rules or grant resource consents that allow the taking, damming or diverting or water to exceed the take limit. Takes or diversions that would exceed the take limits should have an appropriate rule structure that avoids over-allocation (eg, prohibited). The NPS-FM now requires plans to state whether flows or levels will affect existing resource consents (clause 3.17(1)(c)). This allows permit holders to assess the effect of that requirement on their water use, and make submissions to the council during the planning process. The plan may also state that permit holders can comply with the terms of the rule, or rules, in stages or over specified periods.
What about new water users?
In healthy rivers it may still be possible to reallocate water and achieve the long-term visions and Te Mana o te Wai. However, when there is degradation, the first priority is to restore the water body. This may mean permit holders either have their allocation reduced or face more frequent restrictions.
Any water allocation to new users must come from reducing existing takes and ensure flows and levels are restored over time. Opportunities to reduce takes could come from more efficient water use (using less water for the same use) or water storage (either from water harvesting at high flows, or harvesting and storing rainfall). Councils must consider these options with tangata whenua and their communities.
Reducing water use
If achieving new flows and levels means reducing the existing takes (lower take limits), water use may need to be reduced. More efficient use (Policy 11 in the NPS-FM) may be one method. If this is not enough, existing takes may need to be reduced, with some reallocation of water.
Figure 10 shows the tension when allocating water between:
- total amount that can be taken (allocation)
- how reliable it is for users (flow and level restrictions)
- how much we leave for the environment (minimum flow and level).
Councils must follow Te Mana o te Wai when allocating water. Priority goes first to the health and well-being of water bodies and then to people’s health needs. Within the ‘other well-being’ matters, the community may choose its priorities, consistent with Te Mana o te Wai.
Figure 10: ‘Iron triangle’ of water allocation
If a water body is over-allocated, councils may need to phase in the reduction over a period of years. This will allow users time to adjust. There will be implications for users (eg, irrigators). Councils should be upfront with the community about the reductions.
Suggestions for councils and communities
- Align consent expiry dates so they can be reviewed at the same time.
- Build climate resilience into take limits, flows and levels, especially for farming areas with lower takes. Councils can give direction and assistance, improving water-use resilience. This could include on-farm resilience practices that rely less on irrigation, where droughts are predicted to become more common. Achieving Te mana o te Wai and responding to climate change may mean less long-term certainty for users and consent holders, however, in order for the system to be more resilient, there needs to be a degree of flexibility, particularly as new climate science emerges. Forward thinking is critical and may be best achieved by informing permit holders that their permit is not permanent and will be reviewed in relation to increased low flow.
- Think about the implications of consent timeframes and whether to align with national and regional planning frameworks. For example, 10-year consents align with plan timeframes while giving resource users enough certainty to make investment decisions, but not too long (30 years) to be able to adjust water takes or reconsider allocations.
- Keep rules as simple as possible. Avoid complicating the freshwater accounting and compliance, monitoring and enforcement process (eg, many single water takes can make record-keeping difficult and costly for councils).
Water storage
Water storage is an option to use non-critical parts of the flow during low-flow periods when the water body is not stressed, which increases the allocation back to the river.
Stored water must not be used to expand or intensify land use that would breach the resource use limits. Councils must clearly set out the limits on total land use and intensity for different land types in a catchment.
Clause 3.17: Identifying water takes
July 2022
© Ministry for the Environment